Sunshine Coast · South East Queensland · DA statistics
Building a duplex in Caloundra West: approval rates, timelines and costs
Real outcomes from 35 decided dual-occupancy and multi-unit dwelling applications on Caloundra West properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 35 decided applications in Sunshine Coast, 94% of duplex and dual-occupancy applications in Caloundra West were approved, with a median decision time of 46 days.
94%
Approval rate
33 of 35 decided applications
46 days
Median decision time
Lodgement to decision (n=34)
35
Decided applications
Comparable dual-occupancy and multi-unit dwelling applications
8 Sept 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Caloundra West
Across 35 decided dual-occupancy and multi-unit dwelling applications on Caloundra West properties, 33 were approved — an approval rate of 94%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.
The median time from lodgement to decision was 46 days (measured across the 34 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 35 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Caloundra West
The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCU25/0177 | Approved | 8 Sept 2025 | 71 days |
| POS24/0168 | Approved | 24 Sept 2024 | 22 days |
| 2009/500012.01 | Approved | 2 Aug 2023 | 15 days |
| OPW18/0114.01 | Approved | 8 Aug 2022 | 370 days |
| OPW21/0425 | Approved | 25 Oct 2021 | 76 days |
About this data
These statistics summarise decided development applications recorded against Caloundra West properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.