Building a duplex in Nundah: approval rates, timelines and costs

Real outcomes from 346 decided dual-occupancy and multi-unit dwelling applications on Nundah properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 346 decided applications in Brisbane, 95% of duplex and dual-occupancy applications in Nundah were approved, with a median decision time of 132 days.

95%

Approval rate

330 of 346 decided applications

132 days

Median decision time

Lodgement to decision (n=346)

346

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

23 Apr 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Nundah

Across 346 decided dual-occupancy and multi-unit dwelling applications on Nundah properties, 330 were approved — an approval rate of 95%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 132 days (measured across the 346 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 346 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Nundah

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006890934Approved23 Apr 2026175 days
A006889635Approved25 Feb 2026121 days
A006879532Approved20 Nov 202538 days
A006856629Approved6 Nov 202557 days
A006779789Approved11 Sept 2025108 days

About this data

These statistics summarise decided development applications recorded against Nundah properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.