Moreton Bay · South East Queensland · DA statistics
Townhouse development in Banksia Beach: approval rates, timelines and costs
Real outcomes from 40 decided multiple-dwelling and multi-unit applications on Banksia Beach properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 40 decided applications in Moreton Bay, 93% of townhouse development applications in Banksia Beach were approved, with a median decision time of 84 days.
93%
Approval rate
37 of 40 decided applications
84 days
Median decision time
Lodgement to decision (n=40)
40
Decided applications
Comparable multiple-dwelling and multi-unit applications
28 Oct 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Banksia Beach
Across 40 decided multiple-dwelling and multi-unit applications on Banksia Beach properties, 37 were approved — an approval rate of 93%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.
The median time from lodgement to decision was 84 days (measured across the 40 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 40 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Banksia Beach
The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| DA/2025/0525 | Approved | 28 Oct 2025 | 260 days |
| DA/2025/4308 | Approved | 21 Oct 2025 | 43 days |
| DA/2025/4207 | Approved | 23 Sept 2025 | 21 days |
| DA/2024/4355 | Approved | 13 June 2025 | 259 days |
| DA/2025/0131 | Approved | 2 June 2025 | 137 days |
About this data
These statistics summarise decided development applications recorded against Banksia Beach properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.