Moreton Bay · South East Queensland · Council DA statistics

Development applications in Moreton Bay: approval rates and timelines

Real outcomes from 14,811 decided development applications recorded against Moreton Bay council. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 14,811 decided development applications in Moreton Bay, 98% were approved, with a median decision time of 51 days.

98%

Approval rate

14,497 of 14,811 decided applications

51 days

Median decision time

Lodgement to decision (n=14,789)

14,811

Decided applications

Every decided DA we hold for this council

5

Development types

Residential cohorts broken down below

What the numbers say about Moreton Bay

Based on 14,811 decided development applications recorded against Moreton Bay council, 14,497 were approved — an approval rate of 98%. That reflects councils in this region decide the overwhelming majority of applications in favour of the applicant — most refused proposals are withdrawn or reworked before a formal refusal. These are real, decided applications assessed by the council, not estimates or modelling.

The median time from lodgement to decision was 51 days, measured across the 14,789 applications with both dates recorded. That is a comparatively fast assessment turnaround by South East Queensland standards. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

The breakdown below shows how the main residential development types have fared in Moreton Bay. Past decisions describe how comparable proposals have actually gone — but every site is different, and zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Approval rates by development type in Moreton Bay

Each row summarises the decided applications matching that development-type cohort — the same cohorts our suburb statistics pages use.

Development typeDecidedApproval rateMedian daysMedian infra. charge
Subdivision2,50896%77 days$5,000
Duplex1,05596%75 days
Townhouses1,16496%77 days
Units1,16496%77 days
New house2,15999%50 days

Median infrastructure charges are published only where we hold at least 5 charged decision notices and the median falls in a plausible band; cohorts overlap where an application matches more than one development type.

Busiest suburbs for development in Moreton Bay

Ranked by decided development applications. Suburbs with published statistics pages link through to their approval rates and timelines.

Morayfield1,232 decided DAs
Caboolture1,117 decided DAs
Banksia Beach623 decided DAs
Burpengary591 decided DAs
Burpengary East572 decided DAs
Newport525 decided DAs
Narangba521 decided DAs
Brendale384 decided DAs
North Lakes372 decided DAs
Griffin324 decided DAs

About this data

These statistics summarise decided development applications recorded against Moreton Bay council, current as of 2 July 2026. Council-wide figures span every application type we hold for the council, so they mix simple approvals with complex impact-assessable projects. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Council statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.