Sunshine Coast · South East Queensland · DA statistics

Building a new house in Buddina: approval rates, timelines and costs

Real outcomes from 21 decided dwelling-house applications on Buddina properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 21 decided applications in Sunshine Coast, 71% of new-house applications in Buddina were approved, with a median decision time of 104 days.

71%

Approval rate

15 of 21 decided applications

104 days

Median decision time

Lodgement to decision (n=19)

21

Decided applications

Comparable dwelling-house applications

26 Mar 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Buddina

Across 21 decided dwelling-house applications on Buddina properties, 15 were approved — an approval rate of 71%. That reflects a noticeably tougher track record than most SEQ suburbs, so site selection and application quality matter more here. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.

The median time from lodgement to decision was 104 days (measured across the 19 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 21 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Buddina

The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCU25/0059Withdrawn26 Mar 202514 days
1996/10063.01Approved24 Aug 202328 days
MCU22/0195Approved20 Aug 2023437 days
MCU23/0063Refused20 July 2023129 days
MCU22/0266Approved19 Jan 2023157 days

About this data

These statistics summarise decided development applications recorded against Buddina properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.