Building a duplex in Caloundra: approval rates, timelines and costs

Real outcomes from 152 decided dual-occupancy and multi-unit dwelling applications on Caloundra properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 152 decided applications in Sunshine Coast, 87% of duplex and dual-occupancy applications in Caloundra were approved, with a median decision time of 77 days.

87%

Approval rate

132 of 152 decided applications

77 days

Median decision time

Lodgement to decision (n=150)

152

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

24 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Caloundra

Across 152 decided dual-occupancy and multi-unit dwelling applications on Caloundra properties, 132 were approved — an approval rate of 87%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.

The median time from lodgement to decision was 77 days (measured across the 150 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 152 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Caloundra

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCU25/0185Approved24 Feb 2026240 days
MCU24/0145.01Approved30 Nov 202526 days
OPW25/0322Approved29 Oct 202592 days
MCU25/0217Approved29 Oct 202592 days
MCU24/0319.02Approved29 Sept 20257 days

About this data

These statistics summarise decided development applications recorded against Caloundra properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.