Building a granny flat in Cedar Creek: approval rates, timelines and costs
Real outcomes from 10 decided secondary dwelling (granny flat) applications on Cedar Creek properties, drawn from Logan council records. Data current as of 8 July 2026.
According to Casa Intelligence analysis of 10 decided applications in Logan, 80% of granny flat and secondary dwelling applications in Cedar Creek were approved, with a median decision time of 26 days.
80%
Approval rate
8 of 10 decided applications
26 days
Median decision time
Lodgement to decision (n=10)
10
Decided applications
Comparable secondary dwelling (granny flat) applications
9 July 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Cedar Creek
Across 10 decided secondary dwelling (granny flat) applications on Cedar Creek properties, 8 were approved — an approval rate of 80%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.
The median time from lodgement to decision was 26 days (measured across the 10 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 10 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Cedar Creek
The most recent decided secondary dwelling (granny flat) applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCUR/63/2021 | Approved | 9 July 2025 | 28 days |
| MCUR/70/2023 | Approved | 8 Feb 2024 | 31 days |
| MCUR/70/2023 | Approved | 18 Aug 2023 | 91 days |
| MCUR/298/2022 | Approved | 18 Jan 2023 | 64 days |
| MCUR/63/2021 | Approved | 10 June 2021 | 112 days |
About this data
These statistics summarise decided development applications recorded against Cedar Creek properties in Logan council records, current as of 8 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Own a block in Cedar Creek? Check where it stands — free.
The statistics above describe the suburb. A free block check tells you about your address: Casa Score, zone and overlay position, in seconds.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.