Logan · South East Queensland · DA statistics

Building a new house in Cedar Vale: approval rates, timelines and costs

Real outcomes from 64 decided dwelling-house applications on Cedar Vale properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 64 decided applications in Logan, 95% of new-house applications in Cedar Vale were approved, with a median decision time of 50 days.

95%

Approval rate

61 of 64 decided applications

50 days

Median decision time

Lodgement to decision (n=64)

64

Decided applications

Comparable dwelling-house applications

20 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Cedar Vale

Across 64 decided dwelling-house applications on Cedar Vale properties, 61 were approved — an approval rate of 95%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 50 days (measured across the 64 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 64 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Cedar Vale

The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
CAR/606/2025Approved20 Feb 202698 days
CAR/573/2025Approved9 Feb 2026101 days
BWAP/209/2025Approved22 Jan 202659 days
CAR/594/2025Approved8 Jan 202658 days
BWAP/180/2025Approved18 Dec 202580 days

About this data

These statistics summarise decided development applications recorded against Cedar Vale properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.