Logan · South East Queensland · DA statistics

Unit development in Chambers Flat: approval rates, timelines and costs

Real outcomes from 8 decided multiple-dwelling and multi-unit applications on Chambers Flat properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 8 decided applications in Logan, 100% of unit development applications in Chambers Flat were approved, with a median decision time of 114 days.

100%

Approval rate

8 of 8 decided applications

114 days

Median decision time

Lodgement to decision (n=8)

8

Decided applications

Comparable multiple-dwelling and multi-unit applications

19 June 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Chambers Flat

Across 8 decided multiple-dwelling and multi-unit applications on Chambers Flat properties, 8 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 114 days (measured across the 8 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 8 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Chambers Flat

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
COM/35/2024Approved19 June 2025358 days
COM/12/2017Approved21 Oct 202426 days
COM/12/2017Approved29 Apr 202459 days
COM/12/2017Approved5 Sept 202329 days
MCUI/7/2009Approved22 Apr 202238 days

About this data

These statistics summarise decided development applications recorded against Chambers Flat properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.