Townhouse development in Coes Creek: approval rates, timelines and costs

Real outcomes from 9 decided multiple-dwelling and multi-unit applications on Coes Creek properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 9 decided applications in Sunshine Coast, 100% of townhouse development applications in Coes Creek were approved, with a median decision time of 83 days.

100%

Approval rate

9 of 9 decided applications

83 days

Median decision time

Lodgement to decision (n=9)

9

Decided applications

Comparable multiple-dwelling and multi-unit applications

13 Oct 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Coes Creek

Across 9 decided multiple-dwelling and multi-unit applications on Coes Creek properties, 9 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.

The median time from lodgement to decision was 83 days (measured across the 9 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 9 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Coes Creek

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCU25/0235Approved13 Oct 202553 days
OPW25/0306Approved31 Aug 202540 days
MCU25/0209Approved31 Aug 202540 days
MCU24/0117Approved19 Aug 202499 days
MCU24/0088Approved8 July 202484 days

About this data

These statistics summarise decided development applications recorded against Coes Creek properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.