Sunshine Coast · South East Queensland · DA statistics

Unit development in Eumundi: approval rates, timelines and costs

Real outcomes from 46 decided multiple-dwelling and multi-unit applications on Eumundi properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 46 decided applications in Sunshine Coast, 87% of unit development applications in Eumundi were approved, with a median decision time of 76 days.

87%

Approval rate

40 of 46 decided applications

76 days

Median decision time

Lodgement to decision (n=45)

46

Decided applications

Comparable multiple-dwelling and multi-unit applications

13 Jan 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Eumundi

Across 46 decided multiple-dwelling and multi-unit applications on Eumundi properties, 40 were approved — an approval rate of 87%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.

The median time from lodgement to decision was 76 days (measured across the 45 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 46 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Eumundi

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCU25/0205Approved13 Jan 2026181 days
OPW25/0297Approved13 Jan 2026181 days
RAL18/0116.06Approved21 Sept 2025376 days
RAL18/0116.04Approved1 Sept 202463 days
RAL18/0116.05Approved1 Sept 202445 days

About this data

These statistics summarise decided development applications recorded against Eumundi properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.