Moreton Bay · South East Queensland · DA statistics

Unit development in Everton Hills: approval rates, timelines and costs

Real outcomes from 13 decided multiple-dwelling and multi-unit applications on Everton Hills properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 13 decided applications in Moreton Bay, 92% of unit development applications in Everton Hills were approved, with a median decision time of 61 days.

92%

Approval rate

12 of 13 decided applications

61 days

Median decision time

Lodgement to decision (n=13)

13

Decided applications

Comparable multiple-dwelling and multi-unit applications

15 July 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Everton Hills

Across 13 decided multiple-dwelling and multi-unit applications on Everton Hills properties, 12 were approved — an approval rate of 92%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.

The median time from lodgement to decision was 61 days (measured across the 13 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 13 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Everton Hills

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
DA/2025/1187Approved15 July 2025118 days
DA/2024/5240Approved9 Dec 202425 days
DA/2024/2826Approved8 Oct 2024103 days
DA/29644/2014/VCHG/5Approved26 Jan 202140 days
DA/38529/2019/VCHG/1Approved13 Nov 202032 days

About this data

These statistics summarise decided development applications recorded against Everton Hills properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.