Brisbane · South East Queensland · DA statistics

Townhouse development in Everton Park: approval rates, timelines and costs

Real outcomes from 158 decided multiple-dwelling and multi-unit applications on Everton Park properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 158 decided applications in Brisbane, 96% of townhouse development applications in Everton Park were approved, with a median decision time of 146 days.

96%

Approval rate

152 of 158 decided applications

146 days

Median decision time

Lodgement to decision (n=157)

158

Decided applications

Comparable multiple-dwelling and multi-unit applications

30 Jan 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Everton Park

Across 158 decided multiple-dwelling and multi-unit applications on Everton Park properties, 152 were approved — an approval rate of 96%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 146 days (measured across the 157 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 158 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Everton Park

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006923043Approved30 Jan 202646 days
A006811769Approved15 Dec 2025157 days
A006794568Approved3 Dec 2025170 days
A006887233Approved6 Nov 202513 days
A006825545Approved15 Aug 202518 days

About this data

These statistics summarise decided development applications recorded against Everton Park properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.