Building a duplex in Forest Glen: approval rates, timelines and costs

Real outcomes from 38 decided dual-occupancy and multi-unit dwelling applications on Forest Glen properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 38 decided applications in Sunshine Coast, 97% of duplex and dual-occupancy applications in Forest Glen were approved, with a median decision time of 50 days.

97%

Approval rate

37 of 38 decided applications

50 days

Median decision time

Lodgement to decision (n=38)

38

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

16 Sept 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Forest Glen

Across 38 decided dual-occupancy and multi-unit dwelling applications on Forest Glen properties, 37 were approved — an approval rate of 97%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.

The median time from lodgement to decision was 50 days (measured across the 38 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 38 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Forest Glen

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCU18/0315.01Approved16 Sept 202536 days
OPW23/0139Approved30 Nov 2023248 days
MCU18/0310.06Approved26 Nov 202394 days
POS23/0026Approved2 July 2023132 days
OPW21/0529Approved13 Dec 202184 days

About this data

These statistics summarise decided development applications recorded against Forest Glen properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.