Subdividing in Hamilton: approval rates, timelines and costs

Real outcomes from 185 decided reconfiguration and subdivision applications on Hamilton properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 185 decided applications in Brisbane, 96% of subdivision applications in Hamilton were approved, with a median decision time of 89 days.

96%

Approval rate

178 of 185 decided applications

89 days

Median decision time

Lodgement to decision (n=185)

185

Decided applications

Comparable reconfiguration and subdivision applications

13 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Hamilton

Across 185 decided reconfiguration and subdivision applications on Hamilton properties, 178 were approved — an approval rate of 96%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 89 days (measured across the 185 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 185 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Hamilton

The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006879536Approved13 Feb 2026123 days
A006875542Approved21 Nov 202545 days
A006733622Approved8 Sept 2025172 days
A006827804Approved6 Aug 20255 days
A006418183Approved17 June 2025560 days

About this data

These statistics summarise decided development applications recorded against Hamilton properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.