Brisbane · South East Queensland · DA statistics
Townhouse development in Herston: approval rates, timelines and costs
Real outcomes from 16 decided multiple-dwelling and multi-unit applications on Herston properties, drawn from Brisbane council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 16 decided applications in Brisbane, 94% of townhouse development applications in Herston were approved, with a median decision time of 188 days.
94%
Approval rate
15 of 16 decided applications
188 days
Median decision time
Lodgement to decision (n=16)
16
Decided applications
Comparable multiple-dwelling and multi-unit applications
15 Apr 2026
Latest decision
Most recent decided application in this cohort
What the numbers say about Herston
Across 16 decided multiple-dwelling and multi-unit applications on Herston properties, 15 were approved — an approval rate of 94%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.
The median time from lodgement to decision was 188 days (measured across the 16 applications in this cohort with both dates recorded). That is a longer-than-typical assessment timeframe — worth building into your project programme. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 16 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Herston
The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| A006935115 | Approved | 15 Apr 2026 | 98 days |
| A006670786 | Approved | 18 Mar 2025 | 99 days |
| A006435813 | Approved | 3 Apr 2024 | 92 days |
| A006248821 | Approved | 6 Sept 2023 | 148 days |
| A006095480 | Approved | 11 Nov 2022 | 70 days |
About this data
These statistics summarise decided development applications recorded against Herston properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.