Brisbane · South East Queensland · DA statistics

Building a duplex in Kangaroo Point: approval rates, timelines and costs

Real outcomes from 133 decided dual-occupancy and multi-unit dwelling applications on Kangaroo Point properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 133 decided applications in Brisbane, 93% of duplex and dual-occupancy applications in Kangaroo Point were approved, with a median decision time of 114 days.

93%

Approval rate

123 of 133 decided applications

114 days

Median decision time

Lodgement to decision (n=132)

133

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

19 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Kangaroo Point

Across 133 decided dual-occupancy and multi-unit dwelling applications on Kangaroo Point properties, 123 were approved — an approval rate of 93%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 114 days (measured across the 132 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 133 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Kangaroo Point

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006899909Approved19 Feb 202698 days
A006279887Approved8 Aug 2025809 days
A006764430Approved18 July 202572 days
A006638536Approved18 June 2025239 days
A006548070Approved30 Jan 2025227 days

About this data

These statistics summarise decided development applications recorded against Kangaroo Point properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.