Building a duplex in Kings Beach: approval rates, timelines and costs
Real outcomes from 119 decided dual-occupancy and multi-unit dwelling applications on Kings Beach properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 119 decided applications in Sunshine Coast, 80% of duplex and dual-occupancy applications in Kings Beach were approved, with a median decision time of 64 days.
80%
Approval rate
95 of 119 decided applications
64 days
Median decision time
Lodgement to decision (n=116)
119
Decided applications
Comparable dual-occupancy and multi-unit dwelling applications
29 Oct 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Kings Beach
Across 119 decided dual-occupancy and multi-unit dwelling applications on Kings Beach properties, 95 were approved — an approval rate of 80%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.
The median time from lodgement to decision was 64 days (measured across the 116 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 119 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Kings Beach
The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCU24/0111.01 | Approved | 29 Oct 2025 | 42 days |
| OPW24/0505 | Withdrawn | 24 Sept 2025 | 282 days |
| MCU24/0342 | Withdrawn | 24 Sept 2025 | 282 days |
| MCU24/0138 | Approved | 10 Sept 2025 | 465 days |
| 2004/500085.02 | Approved | 14 July 2025 | 54 days |
About this data
These statistics summarise decided development applications recorded against Kings Beach properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.