Sunshine Coast · South East Queensland · DA statistics

Building a duplex in Little Mountain: approval rates, timelines and costs

Real outcomes from 75 decided dual-occupancy and multi-unit dwelling applications on Little Mountain properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 75 decided applications in Sunshine Coast, 83% of duplex and dual-occupancy applications in Little Mountain were approved, with a median decision time of 69 days.

83%

Approval rate

62 of 75 decided applications

69 days

Median decision time

Lodgement to decision (n=71)

75

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

26 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Little Mountain

Across 75 decided dual-occupancy and multi-unit dwelling applications on Little Mountain properties, 62 were approved — an approval rate of 83%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.

The median time from lodgement to decision was 69 days (measured across the 71 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 75 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Little Mountain

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCU24/0307Approved26 Feb 2026470 days
MCU24/0313Approved2 Feb 2026442 days
OPW24/0481Approved2 Feb 2026442 days
2002/510009.01Approved3 Nov 202550 days
MCU15/0129.06Approved30 July 202436 days

About this data

These statistics summarise decided development applications recorded against Little Mountain properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.