Logan · South East Queensland · DA statistics
Subdividing in Logan Village: approval rates, timelines and costs
Real outcomes from 131 decided reconfiguration and subdivision applications on Logan Village properties, drawn from Logan council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 131 decided applications in Logan, 92% of subdivision applications in Logan Village were approved, with a median decision time of 24 days.
92%
Approval rate
120 of 131 decided applications
24 days
Median decision time
Lodgement to decision (n=129)
131
Decided applications
Comparable reconfiguration and subdivision applications
20 Jan 2026
Latest decision
Most recent decided application in this cohort
What the numbers say about Logan Village
Across 131 decided reconfiguration and subdivision applications on Logan Village properties, 120 were approved — an approval rate of 92%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.
The median time from lodgement to decision was 24 days (measured across the 129 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 131 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Logan Village
The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| RL/37/2025 | Approved | 20 Jan 2026 | 263 days |
| MCUC/2/2023 | Approved | 5 Dec 2025 | 80 days |
| SP/10/2025 | Approved | 29 Jan 2025 | 6 days |
| RL/89/2024 | Approved | 11 Dec 2024 | 58 days |
| RL/57/2024 | Approved | 28 Oct 2024 | 90 days |
About this data
These statistics summarise decided development applications recorded against Logan Village properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.