Brisbane · South East Queensland · DA statistics

Townhouse development in Lutwyche: approval rates, timelines and costs

Real outcomes from 111 decided multiple-dwelling and multi-unit applications on Lutwyche properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 111 decided applications in Brisbane, 96% of townhouse development applications in Lutwyche were approved, with a median decision time of 128 days.

96%

Approval rate

107 of 111 decided applications

128 days

Median decision time

Lodgement to decision (n=111)

111

Decided applications

Comparable multiple-dwelling and multi-unit applications

22 Apr 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Lutwyche

Across 111 decided multiple-dwelling and multi-unit applications on Lutwyche properties, 107 were approved — an approval rate of 96%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 128 days (measured across the 111 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 111 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Lutwyche

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006909336Approved22 Apr 2026147 days
A006807498Approved19 Dec 2025168 days
A006805411Approved17 Oct 2025109 days
A006732265Approved4 July 2025109 days
A006733579Approved8 May 202549 days

About this data

These statistics summarise decided development applications recorded against Lutwyche properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.