Building a new house in Maroochydore: approval rates, timelines and costs
Real outcomes from 20 decided dwelling-house applications on Maroochydore properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 20 decided applications in Sunshine Coast, 85% of new-house applications in Maroochydore were approved, with a median decision time of 58 days.
85%
Approval rate
17 of 20 decided applications
58 days
Median decision time
Lodgement to decision (n=20)
20
Decided applications
Comparable dwelling-house applications
11 July 2024
Latest decision
Most recent decided application in this cohort
What the numbers say about Maroochydore
Across 20 decided dwelling-house applications on Maroochydore properties, 17 were approved — an approval rate of 85%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.
The median time from lodgement to decision was 58 days (measured across the 20 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 20 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Maroochydore
The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCU10/0005.05 | Approved | 11 July 2024 | 38 days |
| MCU19/0287.02 | Approved | 18 July 2023 | 124 days |
| MCU19/0287.01 | Refused | 25 Oct 2022 | 40 days |
| MCU20/0303 | Approved | 13 Dec 2020 | 49 days |
| MCU19/0287 | Approved | 26 Feb 2020 | 108 days |
About this data
These statistics summarise decided development applications recorded against Maroochydore properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.