Gold Coast · South East Queensland · DA statistics
Unit development in Mermaid Beach: approval rates, timelines and costs
Real outcomes from 40 decided multiple-dwelling and multi-unit applications on Mermaid Beach properties, drawn from Gold Coast council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 40 decided applications in Gold Coast, 98% of unit development applications in Mermaid Beach were approved.
98%
Approval rate
39 of 40 decided applications
—
Median decision time
Not enough dated records
40
Decided applications
Comparable multiple-dwelling and multi-unit applications
24 May 2026
Latest decision
Most recent decided application in this cohort
What the numbers say about Mermaid Beach
Across 40 decided multiple-dwelling and multi-unit applications on Mermaid Beach properties, 39 were approved — an approval rate of 98%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Gold Coast council, not estimates or modelling.
Based on 40 decided applications in Gold Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Mermaid Beach
The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| PN26697/01/DA1 | approved | 24 May 2026 | — |
| PN79890/01/DA3 | approved | 2 Feb 2026 | — |
| PN24317/01/DA1 | approved | 7 Aug 2023 | — |
| PN24244/01/DA2 | approved | 3 Aug 2022 | — |
| PN26646/04/04 | approved | 22 July 2020 | — |
About this data
These statistics summarise decided development applications recorded against Mermaid Beach properties in Gold Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.