Logan · South East Queensland · DA statistics
Building a granny flat in Munruben: approval rates, timelines and costs
Real outcomes from 20 decided secondary dwelling (granny flat) applications on Munruben properties, drawn from Logan council records. Data current as of 8 July 2026.
According to Casa Intelligence analysis of 20 decided applications in Logan, 90% of granny flat and secondary dwelling applications in Munruben were approved, with a median decision time of 28 days.
90%
Approval rate
18 of 20 decided applications
28 days
Median decision time
Lodgement to decision (n=20)
20
Decided applications
Comparable secondary dwelling (granny flat) applications
18 Aug 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Munruben
Across 20 decided secondary dwelling (granny flat) applications on Munruben properties, 18 were approved — an approval rate of 90%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.
The median time from lodgement to decision was 28 days (measured across the 20 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 20 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Munruben
The most recent decided secondary dwelling (granny flat) applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCUR/24/2025 | Approved | 18 Aug 2025 | 154 days |
| MCUR/37/2025 | Approved | 13 June 2025 | 64 days |
| MCUR/86/2023 | Approved | 14 Aug 2024 | 370 days |
| CAR/113/2022 | Approved | 22 June 2022 | 23 days |
| MCUR/338/2021 | Approved | 4 Jan 2022 | 102 days |
About this data
These statistics summarise decided development applications recorded against Munruben properties in Logan council records, current as of 8 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Own a block in Munruben? Check where it stands — free.
The statistics above describe the suburb. A free block check tells you about your address: Casa Score, zone and overlay position, in seconds.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.