Brisbane · South East Queensland · DA statistics

Townhouse development in Murarrie: approval rates, timelines and costs

Real outcomes from 80 decided multiple-dwelling and multi-unit applications on Murarrie properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 80 decided applications in Brisbane, 99% of townhouse development applications in Murarrie were approved, with a median decision time of 146 days.

99%

Approval rate

79 of 80 decided applications

146 days

Median decision time

Lodgement to decision (n=80)

80

Decided applications

Comparable multiple-dwelling and multi-unit applications

23 Jan 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Murarrie

Across 80 decided multiple-dwelling and multi-unit applications on Murarrie properties, 79 were approved — an approval rate of 99%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 146 days (measured across the 80 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 80 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Murarrie

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006822118Approved23 Jan 2026184 days
A006769149Approved8 Oct 2025147 days
A006728863Approved19 Sept 2025191 days
A006619967Approved20 June 2025267 days
A006062494Approved23 Feb 2024583 days

About this data

These statistics summarise decided development applications recorded against Murarrie properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.