Moreton Bay · South East Queensland · DA statistics

Building a new house in Narangba: approval rates, timelines and costs

Real outcomes from 72 decided dwelling-house applications on Narangba properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 72 decided applications in Moreton Bay, 99% of new-house applications in Narangba were approved, with a median decision time of 44 days.

99%

Approval rate

71 of 72 decided applications

44 days

Median decision time

Lodgement to decision (n=72)

72

Decided applications

Comparable dwelling-house applications

11 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Narangba

Across 72 decided dwelling-house applications on Narangba properties, 71 were approved — an approval rate of 99%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.

The median time from lodgement to decision was 44 days (measured across the 72 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 72 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Narangba

The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
DA/2025/6007Approved11 Feb 202677 days
DA/2025/5329Approved5 Jan 202671 days
DA/2025/5368Approved19 Dec 202552 days
DA/2025/5330Approved27 Nov 202532 days
DA/2025/5411Approved13 Nov 202516 days

About this data

These statistics summarise decided development applications recorded against Narangba properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.