Brisbane · South East Queensland · DA statistics

Townhouse development in Newstead: approval rates, timelines and costs

Real outcomes from 33 decided multiple-dwelling and multi-unit applications on Newstead properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 33 decided applications in Brisbane, 97% of townhouse development applications in Newstead were approved, with a median decision time of 129 days.

97%

Approval rate

32 of 33 decided applications

129 days

Median decision time

Lodgement to decision (n=33)

33

Decided applications

Comparable multiple-dwelling and multi-unit applications

29 Nov 2024

Latest decision

Most recent decided application in this cohort

What the numbers say about Newstead

Across 33 decided multiple-dwelling and multi-unit applications on Newstead properties, 32 were approved — an approval rate of 97%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 129 days (measured across the 33 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 33 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Newstead

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006643329Approved29 Nov 202430 days
A006355850Approved2 Feb 2024148 days
A006073622Approved3 Dec 2022122 days
A005883474Approved7 Sept 2022293 days
A005975626Approved12 July 2022109 days

About this data

These statistics summarise decided development applications recorded against Newstead properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.