Sunshine Coast · South East Queensland · DA statistics
Townhouse development in Palmview: approval rates, timelines and costs
Real outcomes from 21 decided multiple-dwelling and multi-unit applications on Palmview properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 21 decided applications in Sunshine Coast, 95% of townhouse development applications in Palmview were approved, with a median decision time of 80 days.
95%
Approval rate
20 of 21 decided applications
80 days
Median decision time
Lodgement to decision (n=20)
21
Decided applications
Comparable multiple-dwelling and multi-unit applications
11 Dec 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Palmview
Across 21 decided multiple-dwelling and multi-unit applications on Palmview properties, 20 were approved — an approval rate of 95%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.
The median time from lodgement to decision was 80 days (measured across the 20 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 21 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Palmview
The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| OPW25/0247 | Approved | 11 Dec 2025 | 183 days |
| RAL25/0042 | Approved | 11 Dec 2025 | 183 days |
| OPW24/0512 | Approved | 24 July 2025 | 220 days |
| OPW24/0508 | Approved | 2 Apr 2025 | 107 days |
| MPC23/0006 | Approved | 24 Feb 2025 | 655 days |
About this data
These statistics summarise decided development applications recorded against Palmview properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.