Brisbane · South East Queensland · DA statistics

Subdividing in Parkinson: approval rates, timelines and costs

Real outcomes from 80 decided reconfiguration and subdivision applications on Parkinson properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 80 decided applications in Brisbane, 93% of subdivision applications in Parkinson were approved, with a median decision time of 67 days.

93%

Approval rate

74 of 80 decided applications

67 days

Median decision time

Lodgement to decision (n=80)

80

Decided applications

Comparable reconfiguration and subdivision applications

8 Apr 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Parkinson

Across 80 decided reconfiguration and subdivision applications on Parkinson properties, 74 were approved — an approval rate of 93%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 67 days (measured across the 80 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 80 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Parkinson

The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006962210Approved8 Apr 202651 days
A006709796Approved18 Sept 2025220 days
A006809953Withdrawn11 Sept 202566 days
A006795195Approved11 Aug 202555 days
A006764526Approved28 May 202521 days

About this data

These statistics summarise decided development applications recorded against Parkinson properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.