Logan · South East Queensland · DA statistics
Building a new house in Riverbend: approval rates, timelines and costs
Real outcomes from 37 decided dwelling-house applications on Riverbend properties, drawn from Logan council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 37 decided applications in Logan, 87% of new-house applications in Riverbend were approved, with a median decision time of 38 days.
87%
Approval rate
32 of 37 decided applications
38 days
Median decision time
Lodgement to decision (n=37)
37
Decided applications
Comparable dwelling-house applications
3 Nov 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Riverbend
Across 37 decided dwelling-house applications on Riverbend properties, 32 were approved — an approval rate of 87%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.
The median time from lodgement to decision was 38 days (measured across the 37 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 37 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Riverbend
The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| BWAP/158/2025 | Approved | 3 Nov 2025 | 56 days |
| BWAP/167/2025 | Approved | 23 Oct 2025 | 38 days |
| BWAP/122/2025 | Approved | 29 Sept 2025 | 66 days |
| CAR/332/2025 | Withdrawn | 11 July 2025 | 11 days |
| BWAP/16/2025 | Approved | 27 May 2025 | 113 days |
About this data
These statistics summarise decided development applications recorded against Riverbend properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.