Townhouse development in Sherwood: approval rates, timelines and costs

Real outcomes from 113 decided multiple-dwelling and multi-unit applications on Sherwood properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 113 decided applications in Brisbane, 93% of townhouse development applications in Sherwood were approved, with a median decision time of 168 days.

93%

Approval rate

105 of 113 decided applications

168 days

Median decision time

Lodgement to decision (n=113)

113

Decided applications

Comparable multiple-dwelling and multi-unit applications

17 Dec 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Sherwood

Across 113 decided multiple-dwelling and multi-unit applications on Sherwood properties, 105 were approved — an approval rate of 93%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 168 days (measured across the 113 applications in this cohort with both dates recorded). That is a longer-than-typical assessment timeframe — worth building into your project programme. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 113 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Sherwood

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006852722Approved17 Dec 2025103 days
A006379482Approved12 Dec 2025795 days
A006846827Approved9 Sept 202513 days
A006671026Approved19 June 2025192 days
A006634363Approved3 Feb 2025108 days

About this data

These statistics summarise decided development applications recorded against Sherwood properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.