Unit development in Springwood: approval rates, timelines and costs

Real outcomes from 59 decided multiple-dwelling and multi-unit applications on Springwood properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 59 decided applications in Logan, 92% of unit development applications in Springwood were approved, with a median decision time of 32 days.

92%

Approval rate

54 of 59 decided applications

32 days

Median decision time

Lodgement to decision (n=58)

59

Decided applications

Comparable multiple-dwelling and multi-unit applications

26 Mar 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Springwood

Across 59 decided multiple-dwelling and multi-unit applications on Springwood properties, 54 were approved — an approval rate of 92%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 32 days (measured across the 58 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 59 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Springwood

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCUC/27/2019Withdrawn26 Mar 202527 days
MCUC/93/2024Approved19 Sept 202437 days
COM/63/2017Approved5 Aug 202427 days
MCUC/157/2023Refused15 July 2024214 days
MCUC/75/2023Approved1 May 2024316 days

About this data

These statistics summarise decided development applications recorded against Springwood properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.