Brisbane · South East Queensland · DA statistics

Unit development in Taigum: approval rates, timelines and costs

Real outcomes from 19 decided multiple-dwelling and multi-unit applications on Taigum properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 19 decided applications in Brisbane, 100% of unit development applications in Taigum were approved, with a median decision time of 95 days.

100%

Approval rate

19 of 19 decided applications

95 days

Median decision time

Lodgement to decision (n=19)

19

Decided applications

Comparable multiple-dwelling and multi-unit applications

15 Dec 2023

Latest decision

Most recent decided application in this cohort

What the numbers say about Taigum

Across 19 decided multiple-dwelling and multi-unit applications on Taigum properties, 19 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 95 days (measured across the 19 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 19 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Taigum

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006269852Approved15 Dec 2023219 days
A006164349Approved10 Oct 2023308 days
A005059813Approved8 Feb 201995 days
A004713462Approved27 Sept 201755 days
A004217533Approved29 Aug 2016349 days

About this data

These statistics summarise decided development applications recorded against Taigum properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.