Building a duplex in Taringa: approval rates, timelines and costs

Real outcomes from 171 decided dual-occupancy and multi-unit dwelling applications on Taringa properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 171 decided applications in Brisbane, 92% of duplex and dual-occupancy applications in Taringa were approved, with a median decision time of 167 days.

92%

Approval rate

158 of 171 decided applications

167 days

Median decision time

Lodgement to decision (n=171)

171

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

25 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Taringa

Across 171 decided dual-occupancy and multi-unit dwelling applications on Taringa properties, 158 were approved — an approval rate of 92%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 167 days (measured across the 171 applications in this cohort with both dates recorded). That is a longer-than-typical assessment timeframe — worth building into your project programme. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 171 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Taringa

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A006809713Approved25 Feb 2026233 days
A006815044Approved20 Feb 2026220 days
A006504068Approved6 Feb 2026660 days
A006806705Approved14 Jan 2026195 days
A006855292Approved24 Oct 202546 days

About this data

These statistics summarise decided development applications recorded against Taringa properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.