Sunshine Coast · South East Queensland · DA statistics
Subdividing in Weyba Downs: approval rates, timelines and costs
Real outcomes from 10 decided reconfiguration and subdivision applications on Weyba Downs properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 10 decided applications in Sunshine Coast, 100% of subdivision applications in Weyba Downs were approved, with a median decision time of 32 days.
100%
Approval rate
10 of 10 decided applications
32 days
Median decision time
Lodgement to decision (n=9)
10
Decided applications
Comparable reconfiguration and subdivision applications
26 Oct 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Weyba Downs
Across 10 decided reconfiguration and subdivision applications on Weyba Downs properties, 10 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.
The median time from lodgement to decision was 32 days (measured across the 9 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 10 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Weyba Downs
The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| OPW25/0259 | Approved | 26 Oct 2025 | 130 days |
| MCU25/0168 | Approved | 26 Oct 2025 | 130 days |
| OPW24/0182 | Approved | 24 June 2024 | 49 days |
| POS20/0006 | Approved | 23 Nov 2020 | 32 days |
| MCU99/8141.01 | Approved | 24 July 2019 | 20 days |
About this data
These statistics summarise decided development applications recorded against Weyba Downs properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.