Moreton Bay · South East Queensland · DA statistics
Subdividing in Caboolture: approval rates, timelines and costs
Real outcomes from 201 decided reconfiguration and subdivision applications on Caboolture properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 201 decided applications in Moreton Bay, 98% of subdivision applications in Caboolture were approved, with a median decision time of 72 days.
98%
Approval rate
197 of 201 decided applications
72 days
Median decision time
Lodgement to decision (n=201)
201
Decided applications
Comparable reconfiguration and subdivision applications
24 Dec 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Caboolture
Across 201 decided reconfiguration and subdivision applications on Caboolture properties, 197 were approved — an approval rate of 98%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.
The median time from lodgement to decision was 72 days (measured across the 201 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 201 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Caboolture
The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| DA/2025/5624 | Approved | 24 Dec 2025 | 48 days |
| DA/2025/5199 | Approved | 21 Dec 2025 | 61 days |
| DA/2025/4252 | Approved | 21 Dec 2025 | 109 days |
| DA/2025/4310 | Lapsed | 9 Dec 2025 | 92 days |
| DA/2025/5828 | Approved | 7 Dec 2025 | 20 days |
About this data
These statistics summarise decided development applications recorded against Caboolture properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.