Logan · South East Queensland · DA statistics

Building a new house in Beenleigh: approval rates, timelines and costs

Real outcomes from 107 decided dwelling-house applications on Beenleigh properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 107 decided applications in Logan, 90% of new-house applications in Beenleigh were approved, with a median decision time of 40 days.

90%

Approval rate

96 of 107 decided applications

40 days

Median decision time

Lodgement to decision (n=103)

107

Decided applications

Comparable dwelling-house applications

10 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Beenleigh

Across 107 decided dwelling-house applications on Beenleigh properties, 96 were approved — an approval rate of 90%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 40 days (measured across the 103 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 107 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Beenleigh

The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
CAR/589/2025Approved10 Feb 202692 days
MCUR/127/2025Withdrawn30 Jan 202686 days
BWAP/139/2024Withdrawn17 Dec 2025502 days
BWAP/139/2025Approved7 Nov 202584 days
CAR/508/2025Approved6 Nov 202530 days

About this data

These statistics summarise decided development applications recorded against Beenleigh properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.