Building a duplex in Beenleigh: approval rates, timelines and costs
Real outcomes from 48 decided dual-occupancy and duplex applications on Beenleigh properties, drawn from Logan council records. Data current as of 26 July 2026.
Check a Beenleigh block for duplex potential — free, instant.
Zone, overlays and what your address could support — no sign-up to run a check.
According to Casa Intelligence analysis of 48 decided applications in Logan, 88% of duplex and dual-occupancy applications in Beenleigh were approved, with a median decision time of 15 days.
88%
Approval rate
42 of 48 decided applications
15 days
Median decision time
Lodgement to decision (n=47)
48
Decided applications
Comparable dual-occupancy and duplex applications
19 Sept 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Beenleigh
Across 48 decided dual-occupancy and duplex applications on Beenleigh properties, 42 were approved — an approval rate of 88%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.
The median time from lodgement to decision was 15 days (measured across the 47 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 48 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Beenleigh
The most recent decided dual-occupancy and duplex applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCUI/68/2023 | Approved | 19 Sept 2025 | 94 days |
| MCUR/59/2025 | Withdrawn | 15 Aug 2025 | 53 days |
| MCUR/162/2024 | Approved | 23 May 2025 | 164 days |
| COM/30/2018 | Withdrawn | 19 July 2023 | 6 days |
| MCUR/187/2022 | Approved | 10 Nov 2022 | 127 days |
About this data
These statistics summarise decided development applications recorded against Beenleigh properties in Logan council records, current as of 26 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Own a block in Beenleigh? Check where it stands — free.
The statistics above describe the suburb. A free block check tells you about your address: Casa Score, zone and overlay position, in seconds.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.