Moreton Bay · South East Queensland · DA statistics
Building a duplex in Burpengary East: approval rates, timelines and costs
Real outcomes from 13 decided dual-occupancy and duplex applications on Burpengary East properties, drawn from Moreton Bay council records. Data current as of 26 July 2026.
Check a Burpengary East block for duplex potential — free, instant.
Zone, overlays and what your address could support — no sign-up to run a check.
According to Casa Intelligence analysis of 13 decided applications in Moreton Bay, 100% of duplex and dual-occupancy applications in Burpengary East were approved, with a median decision time of 116 days.
100%
Approval rate
13 of 13 decided applications
116 days
Median decision time
Lodgement to decision (n=13)
13
Decided applications
Comparable dual-occupancy and duplex applications
27 Feb 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Burpengary East
Across 13 decided dual-occupancy and duplex applications on Burpengary East properties, 13 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.
The median time from lodgement to decision was 116 days (measured across the 13 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 13 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Burpengary East
The most recent decided dual-occupancy and duplex applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| DA/2025/0433 | Approved | 27 Feb 2025 | 22 days |
| DA/2022/2325 | Approved | 16 Nov 2022 | 148 days |
| DA/39518/2019/V2D | Approved | 27 Nov 2019 | 55 days |
| DA/34872/2017/VCHG/1 | Approved | 16 July 2019 | 328 days |
| DA/35626/2018/V2D | Approved | 17 Apr 2018 | 75 days |
About this data
These statistics summarise decided development applications recorded against Burpengary East properties in Moreton Bay council records, current as of 26 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Own a block in Burpengary East? Check where it stands — free.
The statistics above describe the suburb. A free block check tells you about your address: Casa Score, zone and overlay position, in seconds.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.