Moreton Bay · South East Queensland · DA statistics
Building a duplex in Caboolture: approval rates, timelines and costs
Real outcomes from 78 decided dual-occupancy and multi-unit dwelling applications on Caboolture properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 78 decided applications in Moreton Bay, 97% of duplex and dual-occupancy applications in Caboolture were approved, with a median decision time of 88 days.
97%
Approval rate
76 of 78 decided applications
88 days
Median decision time
Lodgement to decision (n=78)
78
Decided applications
Comparable dual-occupancy and multi-unit dwelling applications
27 Nov 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Caboolture
Across 78 decided dual-occupancy and multi-unit dwelling applications on Caboolture properties, 76 were approved — an approval rate of 97%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.
The median time from lodgement to decision was 88 days (measured across the 78 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 78 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Caboolture
The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| DA/2025/4365 | Approved | 27 Nov 2025 | 79 days |
| DA/2024/3304 | Refused | 12 Nov 2025 | 474 days |
| DA/2025/4241 | Approved | 7 Nov 2025 | 65 days |
| DA/2025/3523 | Approved | 2 Nov 2025 | 97 days |
| DA/2025/1487 | Approved | 24 Sept 2025 | 173 days |
About this data
These statistics summarise decided development applications recorded against Caboolture properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.