Brisbane · South East Queensland · DA statistics

Building a new house in Fortitude Valley: approval rates, timelines and costs

Real outcomes from 21 decided dwelling-house applications on Fortitude Valley properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 21 decided applications in Brisbane, 95% of new-house applications in Fortitude Valley were approved, with a median decision time of 113 days.

95%

Approval rate

20 of 21 decided applications

113 days

Median decision time

Lodgement to decision (n=21)

21

Decided applications

Comparable dwelling-house applications

23 Mar 2018

Latest decision

Most recent decided application in this cohort

What the numbers say about Fortitude Valley

Across 21 decided dwelling-house applications on Fortitude Valley properties, 20 were approved — an approval rate of 95%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 113 days (measured across the 21 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 21 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Fortitude Valley

The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A004792577Approved23 Mar 2018126 days
A004144338Approved16 Nov 2015164 days
A003096771Approved26 Oct 2011145 days
A002843374Approved8 July 2011373 days
A002258020Approved25 Sept 2009220 days

About this data

These statistics summarise decided development applications recorded against Fortitude Valley properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.