Building a new house in Gordon Park: approval rates, timelines and costs
Real outcomes from 76 decided dwelling-house applications on Gordon Park properties, drawn from Brisbane council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 76 decided applications in Brisbane, 99% of new-house applications in Gordon Park were approved, with a median decision time of 34 days.
99%
Approval rate
75 of 76 decided applications
34 days
Median decision time
Lodgement to decision (n=76)
76
Decided applications
Comparable dwelling-house applications
2 May 2019
Latest decision
Most recent decided application in this cohort
What the numbers say about Gordon Park
Across 76 decided dwelling-house applications on Gordon Park properties, 75 were approved — an approval rate of 99%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.
The median time from lodgement to decision was 34 days (measured across the 76 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 76 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Gordon Park
The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| A005174788 | Approved | 2 May 2019 | 15 days |
| A005077112 | Approved | 13 Feb 2019 | 76 days |
| A004406363 | Withdrawn | 23 Mar 2017 | 284 days |
| A004171273 | Approved | 28 July 2015 | 13 days |
| A004098484 | Approved | 29 May 2015 | 51 days |
About this data
These statistics summarise decided development applications recorded against Gordon Park properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.