Moreton Bay · South East Queensland · DA statistics

Subdividing in Kallangur: approval rates, timelines and costs

Real outcomes from 38 decided reconfiguration and subdivision applications on Kallangur properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 38 decided applications in Moreton Bay, 95% of subdivision applications in Kallangur were approved, with a median decision time of 76 days.

95%

Approval rate

36 of 38 decided applications

76 days

Median decision time

Lodgement to decision (n=38)

38

Decided applications

Comparable reconfiguration and subdivision applications

4 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Kallangur

Across 38 decided reconfiguration and subdivision applications on Kallangur properties, 36 were approved — an approval rate of 95%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.

The median time from lodgement to decision was 76 days (measured across the 38 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 38 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Kallangur

The most recent decided reconfiguration and subdivision applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
DA/2025/2259Approved4 Feb 2026259 days
DA/2025/5849Lapsed15 Jan 202658 days
DA/2025/3238Approved1 Nov 2025114 days
DA/2025/2936Approved24 Sept 202591 days
DA/2024/4095Approved16 May 2025245 days

About this data

These statistics summarise decided development applications recorded against Kallangur properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.