Logan · South East Queensland · DA statistics
Townhouse development in Loganholme: approval rates, timelines and costs
Real outcomes from 147 decided multiple-dwelling and multi-unit applications on Loganholme properties, drawn from Logan council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 147 decided applications in Logan, 96% of townhouse development applications in Loganholme were approved, with a median decision time of 30 days.
96%
Approval rate
141 of 147 decided applications
30 days
Median decision time
Lodgement to decision (n=145)
147
Decided applications
Comparable multiple-dwelling and multi-unit applications
22 Dec 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Loganholme
Across 147 decided multiple-dwelling and multi-unit applications on Loganholme properties, 141 were approved — an approval rate of 96%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.
The median time from lodgement to decision was 30 days (measured across the 145 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 147 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Loganholme
The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCUC/81/2021 | Approved | 22 Dec 2025 | 392 days |
| MCUI/37/2025 | Approved | 2 Dec 2025 | 137 days |
| MCUI/62/2024 | Approved | 20 Nov 2025 | 133 days |
| MCUC/155/2024 | Approved | 7 Oct 2025 | 295 days |
| MCUC/83/2023 | Approved | 8 May 2025 | 671 days |
About this data
These statistics summarise decided development applications recorded against Loganholme properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.