Logan · South East Queensland · DA statistics

Townhouse development in Loganlea: approval rates, timelines and costs

Real outcomes from 230 decided multiple-dwelling and multi-unit applications on Loganlea properties, drawn from Logan council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 230 decided applications in Logan, 91% of townhouse development applications in Loganlea were approved, with a median decision time of 22 days.

91%

Approval rate

209 of 230 decided applications

22 days

Median decision time

Lodgement to decision (n=226)

230

Decided applications

Comparable multiple-dwelling and multi-unit applications

19 Feb 2026

Latest decision

Most recent decided application in this cohort

What the numbers say about Loganlea

Across 230 decided multiple-dwelling and multi-unit applications on Loganlea properties, 209 were approved — an approval rate of 91%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Logan council, not estimates or modelling.

The median time from lodgement to decision was 22 days (measured across the 226 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 230 decided applications in Logan, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Loganlea

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
BWAP/205/2025Approved19 Feb 202694 days
MCUI/24/2016Approved4 Nov 2025109 days
MCUC/82/2025Approved14 Aug 20257 days
MCUR/52/2025Approved31 July 202564 days
SP/57/2025Approved17 June 202533 days

About this data

These statistics summarise decided development applications recorded against Loganlea properties in Logan council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.