Townhouse development in Mooloolaba: approval rates, timelines and costs
Real outcomes from 183 decided multiple-dwelling and multi-unit applications on Mooloolaba properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 183 decided applications in Sunshine Coast, 87% of townhouse development applications in Mooloolaba were approved, with a median decision time of 61 days.
87%
Approval rate
159 of 183 decided applications
61 days
Median decision time
Lodgement to decision (n=183)
183
Decided applications
Comparable multiple-dwelling and multi-unit applications
6 Nov 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Mooloolaba
Across 183 decided multiple-dwelling and multi-unit applications on Mooloolaba properties, 159 were approved — an approval rate of 87%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.
The median time from lodgement to decision was 61 days (measured across the 183 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 183 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Mooloolaba
The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| MCU16/0127.03 | Approved | 6 Nov 2025 | 84 days |
| MCU17/2065.02 | Approved | 21 Oct 2025 | 50 days |
| MCU24/0332 | Approved | 13 May 2025 | 159 days |
| MCU22/0214.01 | Approved | 12 May 2025 | 442 days |
| OPW24/0450 | Approved | 8 May 2025 | 184 days |
About this data
These statistics summarise decided development applications recorded against Mooloolaba properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.