Sunshine Coast · South East Queensland · DA statistics

Unit development in Mooloolaba: approval rates, timelines and costs

Real outcomes from 184 decided multiple-dwelling and multi-unit applications on Mooloolaba properties, drawn from Sunshine Coast council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 184 decided applications in Sunshine Coast, 87% of unit development applications in Mooloolaba were approved, with a median decision time of 61 days.

87%

Approval rate

160 of 184 decided applications

61 days

Median decision time

Lodgement to decision (n=184)

184

Decided applications

Comparable multiple-dwelling and multi-unit applications

6 Nov 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about Mooloolaba

Across 184 decided multiple-dwelling and multi-unit applications on Mooloolaba properties, 160 were approved — an approval rate of 87%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Sunshine Coast council, not estimates or modelling.

The median time from lodgement to decision was 61 days (measured across the 184 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 184 decided applications in Sunshine Coast, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Mooloolaba

The most recent decided multiple-dwelling and multi-unit applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
MCU16/0127.03Approved6 Nov 202584 days
MCU17/2065.02Approved21 Oct 202550 days
MCU24/0332Approved13 May 2025159 days
MCU22/0214.01Approved12 May 2025442 days
OPW24/0450Approved8 May 2025184 days

About this data

These statistics summarise decided development applications recorded against Mooloolaba properties in Sunshine Coast council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.