Building a duplex in North Lakes: approval rates, timelines and costs
Real outcomes from 10 decided dual-occupancy and duplex applications on North Lakes properties, drawn from Moreton Bay council records. Data current as of 26 July 2026.
Check a North Lakes block for duplex potential — free, instant.
Zone, overlays and what your address could support — no sign-up to run a check.
According to Casa Intelligence analysis of 10 decided applications in Moreton Bay, 100% of duplex and dual-occupancy applications in North Lakes were approved, with a median decision time of 92 days.
100%
Approval rate
10 of 10 decided applications
92 days
Median decision time
Lodgement to decision (n=10)
10
Decided applications
Comparable dual-occupancy and duplex applications
23 Oct 2024
Latest decision
Most recent decided application in this cohort
What the numbers say about North Lakes
Across 10 decided dual-occupancy and duplex applications on North Lakes properties, 10 were approved — an approval rate of 100%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.
The median time from lodgement to decision was 92 days (measured across the 10 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 10 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in North Lakes
The most recent decided dual-occupancy and duplex applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| DA/2024/3731 | Approved | 23 Oct 2024 | 58 days |
| DA/2024/0537 | Approved | 25 July 2024 | 163 days |
| DA/2022/1044 | Approved | 8 July 2022 | 106 days |
| DA/2021/0903 | Approved | 23 Aug 2021 | 166 days |
| DA/39443/2019/V2D | Approved | 10 Feb 2020 | 139 days |
About this data
These statistics summarise decided development applications recorded against North Lakes properties in Moreton Bay council records, current as of 26 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Own a block in North Lakes? Check where it stands — free.
The statistics above describe the suburb. A free block check tells you about your address: Casa Score, zone and overlay position, in seconds.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.