Moreton Bay · South East Queensland · DA statistics

Building a duplex in North Lakes: approval rates, timelines and costs

Real outcomes from 35 decided dual-occupancy and multi-unit dwelling applications on North Lakes properties, drawn from Moreton Bay council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 35 decided applications in Moreton Bay, 97% of duplex and dual-occupancy applications in North Lakes were approved, with a median decision time of 79 days.

97%

Approval rate

34 of 35 decided applications

79 days

Median decision time

Lodgement to decision (n=35)

35

Decided applications

Comparable dual-occupancy and multi-unit dwelling applications

19 Sept 2025

Latest decision

Most recent decided application in this cohort

What the numbers say about North Lakes

Across 35 decided dual-occupancy and multi-unit dwelling applications on North Lakes properties, 34 were approved — an approval rate of 97%. That reflects a strong track record for this kind of proposal. These are real, decided applications assessed by the Moreton Bay council, not estimates or modelling.

The median time from lodgement to decision was 79 days (measured across the 35 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 35 decided applications in Moreton Bay, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in North Lakes

The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
DA/2025/3475Approved19 Sept 202557 days
DA/2024/5248Approved26 Aug 2025284 days
DA/2024/5950Approved17 July 2025207 days
DA/2024/3731Approved23 Oct 202458 days
DA/2024/0537Approved25 July 2024163 days

About this data

These statistics summarise decided development applications recorded against North Lakes properties in Moreton Bay council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.