Building a duplex in Red Hill: approval rates, timelines and costs
Real outcomes from 49 decided dual-occupancy and multi-unit dwelling applications on Red Hill properties, drawn from Brisbane council records. Data current as of 2 July 2026.
According to Casa Intelligence analysis of 49 decided applications in Brisbane, 88% of duplex and dual-occupancy applications in Red Hill were approved, with a median decision time of 123 days.
88%
Approval rate
43 of 49 decided applications
123 days
Median decision time
Lodgement to decision (n=49)
49
Decided applications
Comparable dual-occupancy and multi-unit dwelling applications
19 Feb 2025
Latest decision
Most recent decided application in this cohort
What the numbers say about Red Hill
Across 49 decided dual-occupancy and multi-unit dwelling applications on Red Hill properties, 43 were approved — an approval rate of 88%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.
The median time from lodgement to decision was 123 days (measured across the 49 applications in this cohort with both dates recorded). That is a fairly typical assessment timeframe for South East Queensland. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.
Based on 49 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.
Recent decisions in Red Hill
The most recent decided dual-occupancy and multi-unit dwelling applications in this cohort, cited by real council application number so you can verify each one yourself.
| Application | Decision | Decided | Days to decision |
|---|---|---|---|
| A006688296 | Approved | 19 Feb 2025 | 41 days |
| A005975016 | Approved | 14 July 2023 | 477 days |
| A005879306 | Approved | 28 July 2022 | 258 days |
| A005676777 | Approved | 6 July 2021 | 123 days |
| A005706669 | Approved | 14 June 2021 | 63 days |
About this data
These statistics summarise decided development applications recorded against Red Hill properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.
Find out what these numbers mean for your site
Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.