Building a new house in Red Hill: approval rates, timelines and costs

Real outcomes from 159 decided dwelling-house applications on Red Hill properties, drawn from Brisbane council records. Data current as of 2 July 2026.

According to Casa Intelligence analysis of 159 decided applications in Brisbane, 89% of new-house applications in Red Hill were approved, with a median decision time of 52 days.

89%

Approval rate

141 of 159 decided applications

52 days

Median decision time

Lodgement to decision (n=159)

159

Decided applications

Comparable dwelling-house applications

3 Dec 2020

Latest decision

Most recent decided application in this cohort

What the numbers say about Red Hill

Across 159 decided dwelling-house applications on Red Hill properties, 141 were approved — an approval rate of 89%. That reflects a solid, though not automatic, track record for this kind of proposal. These are real, decided applications assessed by the Brisbane council, not estimates or modelling.

The median time from lodgement to decision was 52 days (measured across the 159 applications in this cohort with both dates recorded). That is a comparatively fast assessment turnaround. Individual applications vary widely with information requests, referrals and the assessment pathway that applies to the specific site.

Based on 159 decided applications in Brisbane, these figures describe how comparable proposals have actually fared — but every site is different. Zoning, overlays, lot dimensions and the assessment pathway for your specific parcel decide what is realistic for your project.

Recent decisions in Red Hill

The most recent decided dwelling-house applications in this cohort, cited by real council application number so you can verify each one yourself.

ApplicationDecisionDecidedDays to decision
A005563262Approved3 Dec 202058 days
A005334155Approved27 Mar 2020127 days
A005267552Withdrawn13 Dec 2019113 days
A005205413Approved25 July 201955 days
A005061641Approved21 Feb 2019105 days

About this data

These statistics summarise decided development applications recorded against Red Hill properties in Brisbane council records, current as of 2 July 2026. Past decisions describe how comparable proposals have fared — they do not guarantee, and cannot predict, the outcome of any future application. Council assesses every application on its merits against the planning scheme that applies at the time. This page is general information, not planning or legal advice: what is achievable on a specific site depends on its zoning, overlays, lot dimensions and assessment pathway.

For your specific address

Find out what these numbers mean for your site

Suburb statistics tell you the odds. A Preliminary Planning Report tells you where your address stands: approval likelihood, code vs impact pathway, constraints, costs and comparable approved DAs — prepared by a qualified development professional (Master of Architecture) and delivered in minutes.